In spite of being slated for inauguration by August 15, the ₹78-crore sports hub project remains unfinished, missing yet another deadline.
The latest deadline has been set for November 30, although there are chances that the project may face yet another extension. However, MC authorities maintain that 80 per cent of the work has been completed and that the project will be set by the revised deadline.
The state-of-the-art multipurpose sports complex in Burlton Park is likely to significantly enhance sports infrastructure in Jalandhar, which enjoys a national reputation as a sporting hub.
Two Astroturfs for hockey and a seven-a-side natural grass football ground will be readied under the project. Besides, a shed for practising yoga, a skating rink, tennis, volleyball and basketball courts, judo rink, open gym, synthetic athletics track, cycling track and jogging track are also the part of the project.
The project, which had been initially planned, conceived and declared in September 2008 by the SAD-BJP administration and re-started during the tenure of the last Congress regime, was re-launched by AAP national convener Arvind Kejriwal and Chief Minister Bhagwant Mann on June 11 last year.
As per the first plan declared by former Local Bodies Minister Manoranjan Kalia and former Mayor Rakesh Rathour in September 2008, it was a Rs 130-crore project. It had been decided that a world-class cricket stadium and a hockey stadium will be built.
The rest of the space was to be used for developing other sporting facilities, including football, an all-weather swimming pool, badminton, basketball, volleyball, squash, handball, netball, a shooting range, skating rink, jogging and a cycling track, billiards, snooker, judo, gymnasium, besides a five-star hotel, spa, health club, restaurant, bar, lounges, meeting halls, 70 shops and commercial centres.
Numerous changes were made following that. Municipal Commissioner Surinder Singh stated the work will be finished by November 30.