The National Green Tribunal (NGT), Principal Bench, New Delhi, has taken up a matter concerning alleged violations of environmental norm in the establishment of a bio-CNG plant within the premises of Bhogpur Cooperative Sugar Mills Ltd near here.
The matter is registered with the NGT and was heard by a bench comprising Justice Prakash Shrivastava, Chairperson, Dr A Senthil Vel and Dr Afroz Ahmad, both expert members. The applicants have expressed concern concerning the establishment of the bio-CNG plant by ISD Infrastructure LLP, and its special purpose vehicle, ISD Bio Fuels LLP.
As stated before the Tribunal, the plant is suggested to be established on approximately seven acres of land within the premises of Bhogpur Cooperative Sugar Mills Ltd. It is intended to process around 140 metric tonnes of putrescible industrial waste per day, including press mud, cow dung and other waste, and generate methane-rich biogas, around 120 MT of semi-solid slurry and 1,000 KLD of liquid slurry.
A significant issue raised by the applicants worries the alleged violation of the Central Pollution Control Board (CPCB) guidelines issued in March 2022. Particular reference was made to Guideline 9.4(c), which stipulates, "The composting facility shall not be located within 300 m from the nearest dwelling and 100 m from any well or water course."
The applicants have alleged that residential habitation is situated roughly 100 metres from the eastern boundary wall of the plant and roughly 157 metres from its northern boundary. They have also underlined the presence of an administration primary school, a gurdwara, a temple, a petrol pump and residential colonies in the vicinity of the suggested facility.
It was further brought to the Tribunal's notice that the applicants had earlier approached the Punjab and Haryana High Court at Chandigarh by way of a PIL. By its order dated September 24 last, the High Court disposed of the plea while leaving the issues open for adjudication before the appropriate forum, observing that the applicants could approach the National Green Tribunal.
Taking note of the substantial issues concerning compliance with environmental norms, the NGT has issued notices to the respondents. The respondents have looked for four weeks' time to file their replies. The applicant has been directed to serve the remaining respondents and file an affidavit of service at least one week before the next hearing. The matter has been listed for further hearing on February 16, 2027.
The locals of Bhogpur including several farmers and Congress Adampur MLA Sukhwinder Kumar have raised the matter time and once more. They have also blocked highway to demand stopping of its construction.