In another setback to the Jalandhar Improvement Trust (JIT), the District Consumer Disputes Redressal Commission has directed the trust to refund the money deposited by two allottees of its Indira Puram (Master Gurbanta Singh Enclave) housing programme together with 9 per cent annual interest after finding deficiencies in the delivery of flats and basic amenities.
The two orders, passed on November 23, are anticipated to impose a financial burden of about Rs 34 lakh on the trust, with the payout estimated at almost Rs 17 lakh in each case, including accumulated interest.
Besides the refunds, the commission has also directed the JIT to pay Rs 30,000 each as compensation for mental agony and harassment and Rs 10,000 each towards litigation expenses.
Charanjit Singh was allotted LIG Flat No 116 on the second floor of Block A through a draw of lots held on June 13, 2006 in the first case. He had deposited approximately Rs 4.33 lakh towards the flat in installments.
In the second case, Mohinder Parbhakar was allotted LIG Flat No 256 on the first floor of Block A in the same initiative. He had deposited Rs 4,37,147 in a hope of securing his flat.
Both complainants alleged that the JIT had got their signatures on possession documents in October 2009 without completing the flats and providing vital infrastructure. They maintained that the possession provided was merely on paper as the flats were not fit for human habitation.
They further alleged that the JIT delayed depositing approximately Rs 10.78 lakh called for by Punjab State Power Corporation Limited (PSPCL) for installing electricity infrastructure in the colony. The amount was deposited only on August 6, 2012, nearly three years after the trust commenced offering symbolic possession of the flats.
The JIT contested both complaints claiming that the flats had been wrapped up as per the allotment conditions and that possession had been offered to the allottees in its defence.
Rejecting the trust's arguments, the commission noted that the JIT had did not manage to produce convincing evidence to set up that the flats and the surrounding infrastructure had been finished in all respects.
The commission also noted that the JIT had did not manage to produce the mandatory completion or occupancy certificates. It observed that merely obtaining signatures on possession documents did not sum to valid delivery of possession when vital facilities and statutory requirements remained unfulfilled. Citing earlier judicial rulings, it held that home buyers could not be made to wait indefinitely for possession of incomplete properties.
Hence, the commission directed the JIT to refund the respective amounts deposited by the complainants with 9 per cent annual interest from the dates of the individual payments till realisation. The trust has been given 45 days from the receipt of the orders to comply, failing which it will have to pay an additional 3 per cent annual interest on the deposited amounts.